A manufacturer's on-time delivery rate has dropped from 95% to 80%. How would you find out why?
Pin down what "on time" means and when the drop started, then segment late orders by product, plant and customer. Trace orders through promise, materials, production and shipping to find the stage that slipped. Shorter promised dates or a late supplier are common causes.
Updated
How a 90-point answer starts
Two questions before I start. How is on-time defined, is it against the date we promised or the date the customer asked for?
See the full answer, the 50 and 70 versions, and what moves each score up.
Practice this question freeThe numbers, step by step
1,000 orders a month, with 400 now quoted at three weeks instead of four. The 600/400 split is made up. It shows how splitting late orders points to the stage that slipped.
- Late orders at 95% on time1,000 × 5%
- 50
- Late orders at 80% on time1,000 × 20%
- 200
- Late among the 600 four-week orders600 × 5%
- 30
- Late among the 400 three-week orders200 − 30
- 170
- Share of three-week orders that are late170 ÷ 400
- 42.5%
What the interviewer listens for
- Do you ask how "on time" is defined and when the drop started?
- Do you trace the whole order, from the promise to the truck?
- Do you narrow down with data before walking the factory floor?
- Do you consider that the promise changed and the plant did not?
Common mistakes
- Heading straight to the factory floor.If sales began promising three weeks instead of four, orders show up late with nothing wrong in the plant.
- "On time" needs a date to be measured against.Late against the customer's requested date and late against our own promise are different problems with different owners.
- A 15-point fall is rarely spread evenly, so cut late orders by product, plant and customer before opening any stage.
- Overlooking one late supplier.One late component holds the whole order, so compare supplier delivery over the six months of the slide.
Likely follow-ups
- Of 1,000 orders, 600 quoted at four weeks are 95% on time. How many of the 400 quoted at three weeks are late?That's 170, or 42.5% of them. Only 30 of the 200 late orders are four-week ones, so the plant still hits its old promise and the new quote is the problem.
- Sales says shorter quotes won the business. What would you recommend?Quote three weeks only for products and volumes the plant can make that fast, and four for the rest. Losing a few orders is cheaper than losing customers who stop trusting our dates.
- What if supplier deliveries also slipped in the same months?Check whether the late orders are the ones using that supplier's parts. If they overlap, the supplier comes first, because no quote holds while that part is late.
“The case practice helped me see when I was making things too complicated. Sometimes I just needed to ask one useful question and start there.”
More case openings
- A city wants to cut traffic deaths in half within ten years. How would you approach it?
- A food bank's demand is up 30% while donations are flat. How would you help?
- A carmaker is deciding whether to keep making a key component in-house or buy it from a supplier. How would you approach it?
- A hospital's emergency room wait times have doubled in a year. How would you structure the problem?
- An airline's profits are falling even though it is carrying more passengers. What is going on?
Case interview questionsAll interview questionsFree sample casesOperations case practiceCase interview prep plan
Ready for an interviewer that talks back?
Start the 7-day free trial and run your first full case with the AI interviewer today.
Start your free week